How Long Is the Production Lead Time for FRP Equipment?

author:Jinyang time:2026-07-05 00:00:00 Click:132

Lead time depends on product type, size and order quantity. Below is a typical schedule for orders received after drawings are approved. These are planning figures; the exact date is confirmed with your PI (proforma invoice).

Standard Lead Times

ProductTypical Lead Time
FRP storage tanks (under 50 m³)15-25 days
FRP pipes and fittings10-20 days
FRP gratings (standard size)7-15 days
FRP septic tanks10-20 days
Integrated pump stations20-35 days (pumps / controls included)
Electric sluice gates15-30 days
Cooling tower fill7-15 days
New SMC / compression molds30-45 days + production

What Can Extend Lead Time

Lead time starts after drawing confirmation and deposit. It is extended by: custom resins (vinyl ester, fire-retardant), imported pumps or actuators, site-specific certifications, or large-volume orders during peak season. For urgent projects, we can prioritize production and even split shipments if requested.

How to Get a Firm Date

Send your specification (size, quantity, medium, temperature) and target delivery date. We will confirm a realistic lead time and reserve production capacity for you.

References

  • ISO 9001 — Quality Management System Requirements

联系 Contact us

——  Contact:Ms. Wang

——  Tel:+86 19948391999

——  Email:JYFRP@outlook.com

——  Url:https://www.jinyanggep.com

——  Address:Zaoqiang County, Hengshui City, Hebei Province

contact usAddress:Zaoqiang County, Hengshui City, Hebei Province
contact usMobile:+86 19948391999
contact usWhatsapp:+86 19948391999
Copyright © 2026-2027 https://www.jinyanggep.com. All Rights Reserved Hebei Jinyang Environmental Protection Equipment Co., Ltd.
Mobile terminal
contact