How Long Is the Production Lead Time for FRP Equipment?
author:Jinyang time:2026-07-05 00:00:00 Click:132
Lead time depends on product type, size and order quantity. Below is a typical schedule for orders received after drawings are approved. These are planning figures; the exact date is confirmed with your PI (proforma invoice).
Standard Lead Times
| Product | Typical Lead Time |
|---|---|
| FRP storage tanks (under 50 m³) | 15-25 days |
| FRP pipes and fittings | 10-20 days |
| FRP gratings (standard size) | 7-15 days |
| FRP septic tanks | 10-20 days |
| Integrated pump stations | 20-35 days (pumps / controls included) |
| Electric sluice gates | 15-30 days |
| Cooling tower fill | 7-15 days |
| New SMC / compression molds | 30-45 days + production |
What Can Extend Lead Time
Lead time starts after drawing confirmation and deposit. It is extended by: custom resins (vinyl ester, fire-retardant), imported pumps or actuators, site-specific certifications, or large-volume orders during peak season. For urgent projects, we can prioritize production and even split shipments if requested.
How to Get a Firm Date
Send your specification (size, quantity, medium, temperature) and target delivery date. We will confirm a realistic lead time and reserve production capacity for you.
References
ISO 9001 — Quality Management System Requirements
Recommended Products
Contact us
—— Contact:Ms. Wang
—— Tel:+86 19948391999
—— Email:JYFRP@outlook.com
—— Url:https://www.jinyanggep.com
—— Address:Zaoqiang County, Hengshui City, Hebei Province